Eastern Greenwich Civic Cemter - ExsitingProject Overview

The Town of Greenwich Department of Public Works, Building, Construction & Maintenance Division, is responsible for overseeing the construction of the new Eastern Greenwich Civic Center. The new facility will be titled the Cohen Eastern Greenwich Civic Center, named after its donors of the Steven & Alexandra Cohen Foundation, Inc., and will provide the community with a functional and modern civic center that will meet the needs of the community for generations to come. This project will replace the current building, which was built in 1950. Under the approved plan, a one-story 35,418-square-foot building will be constructed on the existing footprint. This new civic center will include a full-size multi-use gymnasium with roll-out spectator seating; 8,100 square feet of multi-use event space; and three 1,000-square-foot activity rooms, two of which will share a partition that can be opened to create a larger room. The Cohen Eastern Greenwich Civic Center is a Parks and Recreation facilityView the webpage here

The Cohen Eastern Greenwich Civic Center is currently an active construction site and is closed to the public. Those who want to access the tennis courts and playground behind the facility must go around the construction site by walking through the playing fields to the north.

Project Timeline

  • Fall 2024 -- Project completion.
  • Winter 2024 -- Painting of structural and mechanical elements has been completed in the gym and event space. Switchgear was delivered and electrical is continuing to be installed. Mechanical equipment has been installed in the mezzanine areas as well as air handling units and fan coil units in the main space. Ceiling grid installation is starting and final painting has commenced in the office area and activity rooms. Basketball backstops have been installed. Lamp poles for the parking lot were delivered
  • Fall 2023 -- Metal duct work and sprinklers were installed in the gym and event space. Roofing and glass facade installation have begun. Sidewalks, granite curb, and concrete pavers are being installed. Parking lots and the main driveway have been completed with new traffic islands. Landscapers started to install trees in new traffic islands. 
  • Summer 2023 -- The exterior of the building's facade is nearing completion. Interior flooring slabs have been poured and interior construction work continues (plumbing, etc.). Regrading the facility's parking lot across the street has begun.   
  • Spring 2023 -- Crews continued site work and utility work. Underslab building utility work was performed. Roof assembly and exterior brick facade were under construction. 
  • Winter 2023 -- All foundation walls and footings have been installed. Crews are progressing through under-slab utility installation. The erection of building steel commenced. 
  • Fall 2022 --- Completion of demolition activities. Began construction of the new facility's foundation, along with the installation of under-slab utilities. 
  • Summer 2022 -- Abatement of the building prior to demolition was performed. Demolition of the existing Eastern Greenwich Civic Center commenced.