A water main replacement project is scheduled to begin in April 2022 on Woodland Drive in Greenwich. Work is expected to be complete by the end of June. Final paving will then be scheduled in coordination with the Town of Greenwich.

Scope of Work

The project, which will replace approximately 900’ of water main, is part of an ongoing program to improve Aquarion’s water distribution system and to ensure the highest quality water. The upgrades will also help to reduce leaks and water main breaks that can cause service interruptions. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m.

overhead map of Woodland Drive project limits

Schedule

  • Construction to begin in April 2022
  • Completion by the end of June.
  • Restoration and final paving will follow in coordination with the Town of Greenwich.

Contacts

  • Contractor: A.J. Penna & Son Excavating, Konstantinos Georgiadis Phone, (203) 227-4053, ext. 120
  • Engineer/Inspector: Snyder Civil Engineers, Steve Melanson, (860) 604-4633
  • Aquarion Project Manager: John Farrell, (203) 362-3048

Nawthorne Road and Keofferam Road Main Replacement 

Project Goals and Objectives

A water main replacement project is scheduled to begin in April 2022 on the following streets: Nawthorne Road and Keofferam Road in Greenwich.  Final paving will then be scheduled in coordination with the Town of Greenwich.

Scope of Work

The project, which will replace approximately 2700 feet of water main, is part of an ongoing program to improve Aquarion’s water distribution system and to ensure the highest quality water.  The upgrades will also help to reduce leaks and water main breaks that can cause service interruptions. Due to construction, customers should expect minor traffic delays and possible detours during the working hours of 7:00 a.m. to 5:00 p.m. 

The project on Keofferam Road will require that your existing water service be connected to an above ground temporary water main during construction.  It will be transferred over to the new water main once it is complete.

overhead map of Nawthorne Road and Keofferam Road project limits

 

Schedule

  • Construction to begin in April 2022
  • Completion by mid-July.
  • Restoration and final paving will follow in coordination with the Town of Greenwich.

Contacts

  • Contractor:  A.J. Penna & Son Excavating- Konstantinos Georgiadis Phone: (203) 227-4053, ext. 120
  • Engineer/Inspector: Snyder Civil Engineers- Steve Melanson, (860) 604-4633